The Facility Manager's Summer Paving Checklist: Pre-Project to Punch List

A field-tested checklist for facility managers running summer asphalt projects — from pre-bid walkthroughs to the final striping inspection.

Written for: Facility Managers · Property Managers · Maintenance Supervisors
Executive summary

Summer paving projects fail at the edges: missed notifications, skipped pre-cons, vague scope, no punch list. This checklist gives facility managers the structure to catch those failures before they cost the property money.

Pre-bid (60-90 days out)

  • Condition assessment with photos and measurements.
  • Drainage walk during or after a rain event.
  • ADA stall, ramp, and route audit.
  • Tenant/resident notification draft.
  • Insurance certificates and bonding requirements defined.

Bid and award (45-60 days out)

  • Apples-to-apples scope across all bidders.
  • References from 3+ similar properties.
  • Equipment list and crew size confirmed.
  • Warranty terms in writing (not 'industry standard').
  • Clear phasing diagram with dates.

Pre-construction (14-21 days out)

  • Walkthrough with contractor, paving superintendent, and site contact.
  • Final phasing map distributed.
  • Tenant/resident notices delivered.
  • Signage, cones, and barricade plan agreed.
  • ADA route plan signed.
  • Daily start/stop times confirmed.

Want this assessed on your property?

Free written pavement findings from the crew that does the work.

During work

  • Daily morning check-in with paving foreman.
  • Photo log of each completed area.
  • Mix tickets retained.
  • Compaction observations noted.
  • Daily sweep of adjacent open areas.

Punch list (within 7 days of completion)

  • Striping completeness and ADA stall geometry.
  • Catch basin elevations and rings.
  • Edge transitions to concrete.
  • Surface temperature/scuff documentation.
  • Final warranty paperwork signed and filed.
Free download · No cost, no obligation

2026 Commercial Pavement Budget Planner

A contractor-built worksheet for budgeting parking lot and roadway work: cost ranges by scope, a condition-scoring sheet, phasing guidance, a bid-comparison checklist, and the questions to ask before you sign.

We use your email only to send the planner and occasional pavement planning notes. No spam, unsubscribe any time.

Common questions

How long should a punch list take to close?+

Most items within 14 days; weather-dependent items (final striping, sealcoat touch-ups) within 30.

What if we find a defect months later?+

Use the warranty. Document with photos, date, and original mix-ticket reference. Reputable contractors stand behind work; this is why references matter.

Do we need a third-party inspector?+

On larger projects, yes — especially for compaction testing. On smaller lots, a structured punch list and good documentation usually suffice.